Enter India's data centre market with timing, not guesswork.

242 source records, with the capacity reconciliation kept stage-separated: 778.69 MW operating, 499.00 MW under construction and 2,236.00 MW announced/approved/unverified. The combined 3,513.69 MW spans all counted stages; it is not operating capacity. Public-data-only.

242 Registry records · stage-separated capacity · Deep Dive / Team options · dated verified changes
investor-market-entry-hero.png
FOR INVESTORS · POWER REALITY
What an IC actually needs

Not another TAM slide — a substation answer

Illustrative diligence question: Could a site support 50 MW within 24 months at a cost an investor could underwrite? This scenario is not a Gridvik forecast or utility commitment. Gridvik organizes public evidence; it cannot confirm a connection, tariff or delivery schedule.

🗺️

State Selection

Power Readiness Index v0 provides a dated relative research screen across 10 states using available public-source fields. It is not an official rating or a site recommendation; verify local conditions with the relevant utility and counterparties.

Download Index v0 →
🔍

Deep Dive · one-time research

A scoped brief can compare public evidence on land status, sanctioned load, DISCOM filings, connectivity and grant status, with sources and unknowns labelled. It is not lender or utility validation and is not investment advice.

  • Conf 3 = official + confirming
  • Conf 1 = early — we flag it
📊

Capacity stages — never mixed

Operating 778.69 MW · under construction 499.00 MW · announced/approved/unverified 2,236.00 MW. The 3,513.69 MW total spans those counted stages and is not operating capacity. Parent/programme overlaps remain explicit.

Read: Two Scoreboards →

Power and approvals fields relevant to due diligence

Source-dated power and approval details drawn from fragmented public filings; unknowns and estimates are labelled.

Sanctioned Load

Check whether a public filing states the sanctioned load at the relevant substation; 50 MW is only an illustrative diligence scenario.

Headroom

Any status or time range is analyst-derived from dated public evidence; it is not a utility queue or headroom confirmation.

Grant & Disbursal

Policy G.O. vs money out — is the incentive actually paid?

Time-to-Power

A source-based estimate only where dated public milestones support it; an MoU date is not a utility schedule.

See Power Layer fields →
India expansion — Gridvik

Current options for investors

Registry snapshot reconciled 26 October 2026: 242 source records, 130 counted in the capacity reconciliation. Operating 778.69 MW; under construction 499.00 MW; announced/approved/unverified 2,236.00 MW. The 3,513.69 MW figure spans all counted stages and is not operating capacity. The former 2,420.37 MW headline is historical and superseded by the reconciliation.
Display prices in
Free Registry
242 source-linked public records; stage labels and source conflicts remain visible.

Browse Registry →

Deep Dive — one-time
State ₹45,000 · National ₹99,000 · Category ₹1,49,000

Scope a Deep Dive →

Team · annual
3 seats, one category, filters, quarterly lead list, monthly review and verified phase-change alerts: ₹3,50,000 / year.

Request Team licence →

Stages are not interchangeable

Operating, under-construction and announced/approved/unverified capacity are shown separately. The 3,513.69 MW total covers the reconciled counted records across those stages; do not present it as live/operating capacity.