The National Data Center for the North East Region at Amingaon, near Guwahati, was commissioned and operationalised by Yotta on behalf of the National Informatics Centre and inaugurated by the Prime Minister on 14 February 2026. It runs 200 racks at 2 MW of IT load today, scales to 4 MW in the next phase, and is engineered for a total power design capacity of 8 MW — or 8.5 MW on the sanctioned load, depending on which source is read. It was built for ₹348.66 crore, which is ₹41.0 crore per megawatt of design capacity — below the ₹51 to ₹60 crore band that five private operators have disclosed. And it is the first megawatt ever contributed to this registry by Assam or the North-East.
1At a glance
2Two megawatts live, eight and a half designed
| Source | Date | Capacity | Scope |
|---|---|---|---|
| Yotta release | 14 Feb 2026 | 2 MW IT / 8 MW design | 200 racks, 4,000 sq m, G+5 |
| Sentinel Assam | 15 Feb 2026 | 4 MW IT from an initial 2 MW / 8.5 MW | 200 to 400 racks, 43,000 sq ft, 70+ PB |
| ET Infra | 14 Feb 2026 | 8.5 MW sanctioned load | Average 10 kW per rack |
| PIB and NIC | 13 Feb 2026 | Inauguration notice | No capacity stated |
| Press coverage of the cost | Feb to Mar 2026 | ₹348.66 crore | Built cost via NICSI |
| This registry | — | 2 MW counted | Commissioned IT load only |
The 8 MW and 8.5 MW figures are not a contradiction so much as two different measurements: design capacity versus sanctioned load from the distribution utility. The registry records both and counts neither, because only the 2 MW has racks in it.
The 4 MW figure is the one that matters commercially — it is the stated next phase, doubling the IT load, and it is the number that would take Assam from 2 MW to 4 MW in this file.
An 8.5 MW connection serving 2 MW of racks is 76% headroom. That is normal for a government facility built for a twenty-year horizon, and it is also exactly the kind of figure that inflates national totals if counted at face value.
Count the design ceiling across a market and you measure ambition. Count commissioned IT load and you measure capacity. This registry counts the second, always.
The check that makes it defensible is 10 kW per rack. Two hundred racks at 10 kW is 2 MW, which matches the commissioning figure exactly. The building's own rack density confirms the number.
3₹41 crore per megawatt, and why it is below the private band
| Programme | Cost and capacity | ₹ crore per MW | Basis |
|---|---|---|---|
| NDC NER Guwahati | ₹348.66 cr for 8.5 MW | 41.0 | Government build, design capacity |
| NDC NER at 2 MW commissioned | ₹348.66 cr for 2 MW | 174.3 | The same money on live capacity |
| Colt DCS–RMZ | US$1.7bn for 250 MW | 60.1 | Private, two cities |
| CapitaLand Chennai 01 | ₹1,940 cr for 34 MW | 57.1 | Private, urban |
| Yotta D4 | US$750m for 120 MW | 55.3 | Private, AI-ready |
| AirTrunk India | US$6.0m per MW | 53.0 | Private, five sites |
| NTT NAV2 phase one | ₹5,500 cr for 107 MW | 51.4 | Private, 54 acres |
| Private band | — | 51.4 to 60.1 | Five independent disclosures |
₹41.0 crore per megawatt is 20% below the cheapest private build in this registry, and there are four ordinary reasons that do not make it a benchmark.
One: government land, in Assam, at a fraction of Navi Mumbai or Noida prices. Two: a 10 kW per rack specification, which is a conventional enterprise hall and needs none of the liquid cooling, higher floor loading or heavier power distribution that a 130 kW AI rack demands. Three: it is a G+5 building on a 4,000 sq m campus at low land efficiency, so there is no dense multi-storey structure. Four: the denominator is design capacity, and only 2 MW of that 8.5 MW is built out.
At commissioned capacity the same money is ₹174 crore per megawatt — three times the private band — which is what happens when capital is spent on headroom rather than on sellable racks.
Both numbers are true and they describe different things. ₹174 crore per live megawatt is the cost of building for a twenty-year government horizon. ₹41 crore per designed megawatt is the cost of the structure, plant and connection.
The private band of ₹51 to ₹60 crore sits between them because private operators build closer to demand — they construct capacity they can lease.
This is the clearest illustration in the file of why per-megawatt cost is only meaningful when the denominator is stated. The same ₹348.66 crore is 41 or 174 depending on which megawatt you divide by.
4Seismic Zone V, and what that costs
The engineering detail on this facility is more interesting than its capacity, and it explains part of the cost.
| Condition | Response | Why it matters |
|---|---|---|
| Seismic Zone V | Highest Indian seismic risk category | Deep load-bearing piles under the structure |
| High groundwater | Amingaon sits on the Brahmaputra floodplain | Foundation and waterproofing constraints |
| Weak soil strata | Published as a construction challenge | Piling depth and cost |
| Power reliability | DG-backed, redundant UPS and battery | Grid quality in the North-East |
| Cooling | Energy-efficient systems with water treatment | Water availability is the constraint |
| Monitoring | Dedicated NOC, SOC and building management system | Government security requirements |
| Solar | 104 kW rooftop | Small, symbolic of the IGBC Gold rating |
Seismic Zone V is the highest of India’s four seismic zones and covers the entire North-East, Kashmir and the Kutch. Almost no data centre in this registry publishes its seismic design basis, and NDC NER is the only one that names Zone V.
That is a real and unglamorous constraint. Load-bearing piles, heavier structural frames and more conservative foundations all cost money that does not appear as a megawatt, and they are exactly why a facility in Guwahati is not directly comparable to one in Chennai on any per-megawatt basis.
For an investor or a tenant, the useful question about any Indian data centre outside the main five cities is: what seismic zone is it in, and what did you do about it? Almost nobody publishes the answer.
5The North-East as a data centre region
| Measure | MW | Note |
|---|---|---|
| Assam, before this record | 0 | No data centre record existed |
| NDC NER, counted | 2 | Commissioned IT load |
| Assam at design capacity | 8.5 | If fully built out |
| All eight North-Eastern states combined | 2 | One facility |
| Assam as a share of the registry | 0.08% | Of 2,420.4 MW |
| Maharashtra for comparison | 786.4 | 393× Assam |
| West Bengal for comparison | 1.08 | The nearest state with counted capacity |
One facility is the entire North-Eastern data centre market in this registry. Eight states — Assam, Arunachal Pradesh, Manipur, Meghalaya, Mizoram, Nagaland, Sikkim and Tripura — served by two megawatts in Kamrup district.
That is not a criticism of the facility, which is well built and serves a genuine sovereign function. It is a description of Indian data centre geography: capacity follows submarine cable landings, banking and IT services clusters, and the North-East has none of those at scale.
The facility’s stated second role is more interesting than its capacity — it is a disaster recovery centre for other National Data Centres. Geographic diversity is the one thing a data centre in the North-East does better than any facility in Mumbai, and for government systems that requirement cannot be bought any other way.
At 2 MW, this is the smallest single-facility contribution to the register that changes a state from zero to a number. The registry records it because a state that has one data centre is a different market from a state that has none.
6Procurement
7Limits and open questions
- 8 MW and 8.5 MW are both current — design capacity and sanctioned load. Neither is counted.
- 2 MW is commissioned IT load and is what the registry counts.
- ₹348.66 crore is the built cost, reported through NICSI; a separate account cites a Rs 600 crore government grant, and the two are not reconciled.
- 10 kW per rack is an average from government coverage, not a per-hall specification.
- “70+ PB of storage” and “99.98% uptime” are government statements with no measurement basis published.
- The next phase has no date. “Scalable to 4 MW” is not a schedule.
- 2 MW is counted, taking Assam from zero to 0.08% of the national total.
- What would close it. A phase two tender or commissioning date.
8Sources
Sources: the Yotta release of 14 February 2026 on the NDC NER inauguration; Sentinel Assam and CXO Chapter coverage; ET Infra and Awaz The Voice on the sanctioned load and rack capacity; PIB and NIC pre-inauguration notices; Manufacturing Today, Bisinfotech and NewzOnClick; and Data Center Dynamics on the NICSI programme.