Facility record · Verified 26 Oct 2026

NDC NER — Amingaon, GuwahatiBuilt and operated by Yotta Data Services for the National Informatics Centre · Amingaon, Kamrup, Assam · 2 MW IT live · 8.5 MW sanctioned · ₹348.66 crore · Inaugurated 14 February 2026

Record PRJ-215Assam — GuwahatiTier A — commissioned, government-attested8 public sources checkedAdditive: yes — 2 MW counted
Commissioned and liveFirst counted capacity in the North-East₹41 crore per MW at design capacity8 MW or 8.5 MW, unreconciledIT load is 2 MW of an 8.5 MW design
2MW
IT load today
8.5MW
Sanctioned load
200
Racks
10kW
Per rack
₹348.66cr
Built cost
43,056sq ft
Built area

The National Data Center for the North East Region at Amingaon, near Guwahati, was commissioned and operationalised by Yotta on behalf of the National Informatics Centre and inaugurated by the Prime Minister on 14 February 2026. It runs 200 racks at 2 MW of IT load today, scales to 4 MW in the next phase, and is engineered for a total power design capacity of 8 MW — or 8.5 MW on the sanctioned load, depending on which source is read. It was built for ₹348.66 crore, which is ₹41.0 crore per megawatt of design capacity — below the ₹51 to ₹60 crore band that five private operators have disclosed. And it is the first megawatt ever contributed to this registry by Assam or the North-East.

1At a glance

Facility
National Data Center — North East Region (NDC NER)
Location
Amingaon, Kamrup district, near Guwahati, Assam
Owner
National Informatics Centre, Ministry of Electronics and IT
Built and operated by
Yotta Data Services, on a greenfield basis
Inaugurated
14 February 2026, by the Prime Minister
Structure
G+5 on a 4,000 sq m campus; 43,056 sq ft built area
IT load today
2 MW across 200 racks
Rack density
10 kW per rack
Next phase
4 MW IT load; racks expandable to 400
Total power design
8 MW per Yotta; 8.5 MW sanctioned load per government coverage
Built cost
₹348.66 crore — ₹41.0 crore per MW of design capacity
Certification
Tier III, IGBC Gold; 99.98% uptime target with N+1 redundancy
Seismic design
Zone V, deep load-bearing piles, high groundwater and weak soil
Sustainability
104 kW rooftop solar
Storage
70+ PB
Role
Serves all eight North-Eastern states; disaster recovery centre for other National Data Centres
Counted in this registry
2 MW — additive

2Two megawatts live, eight and a half designed

Total power design, 8.5 MWSanctioned load, ET Infra8.5 MWTotal power design, 8 MWYotta operator release8.0 MWIT load, next phaseScalable from the initial 2 MW4.0 MWIT load today200 racks, live since 14 Feb 20262.0 MWNorth-East region counted beforeNo record existed0 MWThe red bar is commissioned capacity. Everything above it is a design ceiling on a 4,000 sq m campus in Seismic Zone V.
Figure 1 — the NDC NER capacity ladder. The 8 and 8.5 MW figures are the same design described two ways; the 4 MW is the next phase; only the 2 MW has racks in it.
What each source says about the same building
SourceDateCapacityScope
Yotta release14 Feb 20262 MW IT / 8 MW design200 racks, 4,000 sq m, G+5
Sentinel Assam15 Feb 20264 MW IT from an initial 2 MW / 8.5 MW200 to 400 racks, 43,000 sq ft, 70+ PB
ET Infra14 Feb 20268.5 MW sanctioned loadAverage 10 kW per rack
PIB and NIC13 Feb 2026Inauguration noticeNo capacity stated
Press coverage of the costFeb to Mar 2026₹348.66 croreBuilt cost via NICSI
This registry—2 MW countedCommissioned IT load only

The 8 MW and 8.5 MW figures are not a contradiction so much as two different measurements: design capacity versus sanctioned load from the distribution utility. The registry records both and counts neither, because only the 2 MW has racks in it.

The 4 MW figure is the one that matters commercially — it is the stated next phase, doubling the IT load, and it is the number that would take Assam from 2 MW to 4 MW in this file.

Why the registry counts the smallest number

An 8.5 MW connection serving 2 MW of racks is 76% headroom. That is normal for a government facility built for a twenty-year horizon, and it is also exactly the kind of figure that inflates national totals if counted at face value.

Count the design ceiling across a market and you measure ambition. Count commissioned IT load and you measure capacity. This registry counts the second, always.

The check that makes it defensible is 10 kW per rack. Two hundred racks at 10 kW is 2 MW, which matches the commissioning figure exactly. The building's own rack density confirms the number.

3₹41 crore per megawatt, and why it is below the private band

The first government-disclosed build cost against the private band
ProgrammeCost and capacity₹ crore per MWBasis
NDC NER Guwahati₹348.66 cr for 8.5 MW41.0Government build, design capacity
NDC NER at 2 MW commissioned₹348.66 cr for 2 MW174.3The same money on live capacity
Colt DCS–RMZUS$1.7bn for 250 MW60.1Private, two cities
CapitaLand Chennai 01₹1,940 cr for 34 MW57.1Private, urban
Yotta D4US$750m for 120 MW55.3Private, AI-ready
AirTrunk IndiaUS$6.0m per MW53.0Private, five sites
NTT NAV2 phase one₹5,500 cr for 107 MW51.4Private, 54 acres
Private band—51.4 to 60.1Five independent disclosures

₹41.0 crore per megawatt is 20% below the cheapest private build in this registry, and there are four ordinary reasons that do not make it a benchmark.

One: government land, in Assam, at a fraction of Navi Mumbai or Noida prices. Two: a 10 kW per rack specification, which is a conventional enterprise hall and needs none of the liquid cooling, higher floor loading or heavier power distribution that a 130 kW AI rack demands. Three: it is a G+5 building on a 4,000 sq m campus at low land efficiency, so there is no dense multi-storey structure. Four: the denominator is design capacity, and only 2 MW of that 8.5 MW is built out.

At commissioned capacity the same money is ₹174 crore per megawatt — three times the private band — which is what happens when capital is spent on headroom rather than on sellable racks.

The lesson a buyer should take from the two figures

Both numbers are true and they describe different things. ₹174 crore per live megawatt is the cost of building for a twenty-year government horizon. ₹41 crore per designed megawatt is the cost of the structure, plant and connection.

The private band of ₹51 to ₹60 crore sits between them because private operators build closer to demand — they construct capacity they can lease.

This is the clearest illustration in the file of why per-megawatt cost is only meaningful when the denominator is stated. The same ₹348.66 crore is 41 or 174 depending on which megawatt you divide by.

4Seismic Zone V, and what that costs

The engineering detail on this facility is more interesting than its capacity, and it explains part of the cost.

Site conditions and what was built for them
ConditionResponseWhy it matters
Seismic Zone VHighest Indian seismic risk categoryDeep load-bearing piles under the structure
High groundwaterAmingaon sits on the Brahmaputra floodplainFoundation and waterproofing constraints
Weak soil strataPublished as a construction challengePiling depth and cost
Power reliabilityDG-backed, redundant UPS and batteryGrid quality in the North-East
CoolingEnergy-efficient systems with water treatmentWater availability is the constraint
MonitoringDedicated NOC, SOC and building management systemGovernment security requirements
Solar104 kW rooftopSmall, symbolic of the IGBC Gold rating

Seismic Zone V is the highest of India’s four seismic zones and covers the entire North-East, Kashmir and the Kutch. Almost no data centre in this registry publishes its seismic design basis, and NDC NER is the only one that names Zone V.

That is a real and unglamorous constraint. Load-bearing piles, heavier structural frames and more conservative foundations all cost money that does not appear as a megawatt, and they are exactly why a facility in Guwahati is not directly comparable to one in Chennai on any per-megawatt basis.

For an investor or a tenant, the useful question about any Indian data centre outside the main five cities is: what seismic zone is it in, and what did you do about it? Almost nobody publishes the answer.

5The North-East as a data centre region

What the North-East contributes to this registry
MeasureMWNote
Assam, before this record0No data centre record existed
NDC NER, counted2Commissioned IT load
Assam at design capacity8.5If fully built out
All eight North-Eastern states combined2One facility
Assam as a share of the registry0.08%Of 2,420.4 MW
Maharashtra for comparison786.4393× Assam
West Bengal for comparison1.08The nearest state with counted capacity

One facility is the entire North-Eastern data centre market in this registry. Eight states — Assam, Arunachal Pradesh, Manipur, Meghalaya, Mizoram, Nagaland, Sikkim and Tripura — served by two megawatts in Kamrup district.

That is not a criticism of the facility, which is well built and serves a genuine sovereign function. It is a description of Indian data centre geography: capacity follows submarine cable landings, banking and IT services clusters, and the North-East has none of those at scale.

The facility’s stated second role is more interesting than its capacity — it is a disaster recovery centre for other National Data Centres. Geographic diversity is the one thing a data centre in the North-East does better than any facility in Mumbai, and for government systems that requirement cannot be bought any other way.

At 2 MW, this is the smallest single-facility contribution to the register that changes a state from zero to a number. The registry records it because a state that has one data centre is a different market from a state that has none.

6Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
Nothing commercially — this is a government facility. Buy it as the only Zone V reference design in India
Where the capacity is
Amingaon, Kamrup, Assam. 2 MW IT, 200 racks, expanding to 4 MW
Who holds the answer
National Informatics Centre owns it; Yotta built and operates it
The one question
When does the 4 MW phase get sanctioned, and who supplies the racks
Why they will answer it
NICSI procurement is published and open to tender
Gridvik estimate
Phase two at 4 MW within three years on government procurement timelines. Labelled an estimate
What changes it
A NICSI tender for phase two, or a published commissioning date
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

7Limits and open questions

  • 8 MW and 8.5 MW are both current — design capacity and sanctioned load. Neither is counted.
  • 2 MW is commissioned IT load and is what the registry counts.
  • ₹348.66 crore is the built cost, reported through NICSI; a separate account cites a Rs 600 crore government grant, and the two are not reconciled.
  • 10 kW per rack is an average from government coverage, not a per-hall specification.
  • “70+ PB of storage” and “99.98% uptime” are government statements with no measurement basis published.
  • The next phase has no date. “Scalable to 4 MW” is not a schedule.
  • 2 MW is counted, taking Assam from zero to 0.08% of the national total.
  • What would close it. A phase two tender or commissioning date.

8Sources

Sources: the Yotta release of 14 February 2026 on the NDC NER inauguration; Sentinel Assam and CXO Chapter coverage; ET Infra and Awaz The Voice on the sanctioned load and rack capacity; PIB and NIC pre-inauguration notices; Manufacturing Today, Bisinfotech and NewzOnClick; and Data Center Dynamics on the NICSI programme.